conveyor-belt-boxesProduction preparation: item to be produced, bills of materials, and ranges

Before starting production, the company must identify the item to be manufactured. They then use bills of materials to list the necessary components, as well as work instructions to define the manufac

Item to be produced:

Once a customer order has been received, the company must create the item(s) to be produced.

Here is the case of a bag manufacturing company:

MASOCIETE received an order for 50 women's tote bags. The production manager then created the Tote bag item and entered all the necessary information about the item.

Implementation:

To create an article, go to Files > Item > Items.

Bill of Materials and ranges

To manufacture a product, its components need to be put together. A set of operating procedures also needs to be created to list all the stages involved in making an item.

Also in the item's description, the company lists the components needed to manufacture the tote bags, for example: 50 pieces of fabric, 50 spools of thread, and 100 handles.

It is also essential to list the production steps, known as workforce, such as: cutting the fabric, preparing the handles, assembling the body of the bag, attaching the handles, and then finishing touches.

Implementation:

While remaining in the item file, open [Production] and fill in the components for manufacturing your item one by one.

Machines, stations, and maintenance: creation of production machines and stations.

Before starting production, the company must register the machines used and the corresponding stations.

Production machine creation

A production machine is used to produce and assemble items to be manufactured as part of a production order.

The company has just acquired a new industrial flatbed sewing machine for assembling tote bags. To integrate it into the management system, the production manager enters the necessary information: machine name (JUKI DDL-8700 sewing machine), type (sewing machine), associated workstation, and production rate. Once the machine is registered, it becomes available to be assigned to manufacturing orders in order to produce and assemble items in the manufacturing process.

Implementation:

To create your new machine in your system, go to Production > Production machine list, then click [[New]].

Now fill in the Label, Station, Establishment, and other required fields such as Brand, Pace, etc.

Don't forget to save.

Production station

When planning production, the workload item allows you to anticipate resource mobilization by viewing available capacity and workload per workshop.

The company plans to launch production of 200 tote bags for the following week. During planning, the manager consults the workload items in the production module to check the available capacity of the sewing machines in the workshop.

Implementation:

To check load items, go to Production > Workload and capacity > Production station.